Why Collision Repair Takes Longer Than Quoted

A repair quoted at twenty hours of labor does not take two and a half working days. The hours are the work; the calendar is the work plus everything waiting in between.

Approval cycles

Hidden damage found during disassembly has to be documented, submitted and approved before it can be repaired. Each round trip adds days, and a complex repair can have several. This is the single biggest cause of slipped dates. See supplements explained.

Parts

Once approved, parts have to arrive. Some come next day; some are on back order with no date. A car can be fully prepared and waiting on one bracket. Substituting a different part often needs another approval, which starts the first problem again.

Paint is a sequence, not a task

Refinishing runs in stages with curing time between them, and those stages cannot be compressed. A booth also serves the whole shop, so a car joins a queue. Color matching on metallics and pearls sometimes needs a test panel before the shop will commit, which is a day well spent rather than a delay.

Calibration and alignment at the end

Recalibration and alignment happen after everything is assembled, and if they are sublet, the car leaves and comes back. A fault found at that stage sends the car backwards.

What a good shop does about it

Tells you the plan, tells you when it changes, and tells you why. The frustrating repairs are rarely the slow ones; they are the ones where nobody explained. Ask for a target date and a reason attached, and ask to be told when either moves.

What you can do

Respond quickly to anything that needs your decision, and check your rental coverage so a delay does not become an unexpected bill.